Independence Road Phase III Project Update
Posted Date:
6/8/2017
Here is the latest news and updates regarding the Independence Road Phase III project. Major construction began in April of 2016 and the target completion date was April 2, 2017 but due to numerous delays it is estimated the project will not be completed until late spring.
Pavement Solutions (PS) is the General Contractor for the construction of the roadway improvements. According to PS's revised construction schedule they are now showing June 30, 2017, as the date to be Substantially Complete. PS has requested an 81 day time extension and the construction engineer, HR Green recommended granting an 11 day time extension to PS. The City Board accepted HRG's recommendation, which extended the contract deadline date to 4/13/17. We are now past this date and liquidated damages are being assessed against the contractor's pay requests until the project is fully complete. 

PS has been excavating along the roadway at Nancy Lane and began pouring the curbs. They are focusing on completing the work at Nancy Lane so that may reopen and then the will work on the main entrance to City Hall. This will be followed by work on John Linn Pl. 

Rosch has completed the north retaining wall and curbing is being installed so that paving can begin. Paving of the both lanes will occur in the next two weeks with two way traffic reopening in two to three weeks. 

Backfilling and final grading on the north side along the recently completed retaining wall will begin soon. Sonotubes for footings for the wrought iron fence will be installed on the south side retaining wall. 

Finish grading and sod placement has continued on the south side of Ind. Rd. and will soon begin on the north side. Grading is still planned for the north side of the roadway and construction of the walking trail will begin soon. 

Two way traffic has been re-established to John Linn Pl. from the City Park/Camelot end of the roadway. 

We will post regular updates to this news feed to keep you posted on the latest project details. If you have additional questions feel free to contact the City Administrator, Michael Padella, at 636.441.2110 ext. 102 or by email

 

Find us on Facebook Follow us on Twitter Get e-Notifications RSS Feeds  
 
City of Weldon Spring    -    5401 Independence Road    -    Weldon Spring, MO 63304
Phone: (636) 441-2110    -    Fax: (636) 441-8495
Contact Us   |   Site Map   |   Powered by MunicipalCMS